Instructed by solicitors acting for Responding Party
Appointed by Responding Party’s solicitors as delay expert in an adjudication where the Referring Party (the Main Contractor) were seeking a significant Adjustment to the Completion Date and relief from exposure to in excess of £1m LADs.
Pyments prepared a rebuttal and alternative assessment of critical delay and the adjudicator decided 100% in the Responding Party’s favour (the Developer).